A new housing development was proposed on a former industrial site in Frome, Somerset. Before development could proceed, the site needed to be levelled by importing soil to upfill low areas by as much as 7 metres, and a 6m high reinforced fill slope built to bound the adjacent River Frome. A variety of foundation solutions were then designed to suit the various geotechnical scenarios within the reformed site.
South West Geotechnical scoped and implemented the ground investigation, and designed and supervised both the earthworks and reinforced fill slope.
The ground investigation comprised 6 cable percussion boreholes, 20 rotary drillholes and 30 trial pits, with associated laboratory and in-situ testing, all carried out with our own resources.
Earthworks monitoring included initial compaction trials on various prospective fill materials to assess optimum compaction requirements, and the checking of compacted fill for in-situ density and strength requirements as filling proceeded. This was done by sand replacement density testing, plate bearing testing, and laboratory triaxial shear strength determination.
After completion of earthworks laying, a 12 month settlement monitoring programme was initiated, to delineate areas of the site where long term settlements would be sufficiently low to permit the use of shallow spread foundations, and those that would require deep (piled) foundations.
Levelling was undertaken with precise digital optical equipment, and a levelling staff designed to have minimal length-change potential with variations in temperature, by D&H Surveys of Chippenham, Wiltshire. The equipment enabled a degree of accuracy of less than 1mm to be achieved.
The 6m high reinforced fill slope was required to be constructed over very soft to soft alluvial clays. Consequently a vibropiled foundation system through the alluvium down to bedrock was required to support the new slope. The new slope was built up using primarily recycled crushed concrete from the former industrial development on the site, and was reinforced with primary geogrid reinforcement at 1m intervals and intervening secondary reinforcement at 0.25m intervals.
The surface was protected using a topsoil filled geocell solution.